GLENN HIGHWAY AT MIRROR LAKE - NOV 2018 EQ PR ROAD CONSTRUCTION through the season
What You Need to Know
  • Crews are finishing up work for the season before moving the project into winter shutdown.
  • Southbound traffic will remain routed onto the median DETOUR through the winter. Drivers should be alert to a reduced speed limit of 55 MPH.
  • The Glenn Highway on- and off-ramps at Mirror Lake, as well as Paradis Lane, are open through the winter.
Project End Result

The Alaska Department of Transportation, in cooperation with HC Contractors, is working to make permanent repairs to the Glenn Highway from MP 23 to 25 where embankment and slope failures occurred during the 2018 earthquake, including reconstructing embankment and structural sections and constructing aggregate columns, as well as installing grading, paving, guardrail, and striping. 

Contractor Information

HC Contractors

Contractor Number
907-488-5983
DOT Number
907-376-9096
Project Area
2

Special Accommodations Contact:

Those people who reside in construction zones and may require special accommodations should call the DOT Highway Construction Engineer at 907-269-0450 (TTY 907-269-0473).

Safety in all construction zones:

  • Traffic fines are double
  • Watch for changing driving surfaces
  • Watch for reduced speed limits
  • Be alert to and follow directions of flaggers
  • Drive with headlights on
  • Allow additional time when traveling
  • Watch for equipment and workers