ROAD CLOSURE: The Kenai Spur Highway is CLOSED from Spruce Avenue to Forest Drive (MP 12) until approximately Monday, August 15 due to culvert installation. Please follow construction signs and flaggers for DETOUR routes to Spruce Avenue, 4th Avenue and back onto the Kenai Spur Highway.

  • Pedestrian traffic may be detoured during construction of the pedestrian pathway.

Traffic Impacts

During culvert replacement, lanes will be reduced to one lane each direction 24 hours a day. Detours will be in place for some of the work. Reduced speeds and flagging operations will be in effect for detours. Night work will be used for asphalt planing and paving.

Project End Result

The Alaska Department of Transportation is working with QAP to preserve the pavement of the Kenai Spur Highway from MP 8 to 12.4. Upon completion, the project area will be repaved, there will be new fish-passage culverts under the roadway, new curb ramps and improvements to pedestrian pathways will be made. This project is scheduled to be complete by September 2017.

More Information

DOT: Engineer Phone: 269-0450
Hotline: 283-0563

From the Project Engineer

Please watch for changes in traffic patterns and for flagging operations. This Project includes the use of traffic and pedestrian detours to more efficiently complete the work and reduce the time spent impacting the traveling public and residents. Thank you for all your patience. Have a wonderful 4th of July weekend!

KENAI SPUR HIGHWAY, MP 8 to 12.4 PAVEMENT PRESERVATION

ROAD CONSTRUCTION through the season

Today's date is:

August 4, 2016

Last updated at: 16:39 August 4, 2016

Map Legend

map legend

Construction Areas Note

Those people who reside in construction zones and may require special accommodations should call the DOT Highway Construction Engineer at 907-269-0450 (TTY 907-269-0473).